Scheduling
- CDI uses Microsoft Project 2003 to prepare the Overall Project Schedule, SIPS (Short interval Production Schedules) and monthly updates of the Overall Project Schedule.
- Network application allows our project team in the field and office to keep up-to-date on the status of the project and its critical scheduling issues.
- We work with the Owner to determine any site conditions and constraints that will affect construction, and incorporate these requirements into the Construction Schedule and Bid Packages.
- Preliminary Project Schedule:
- Critical Dates for Pre-Construction Activities
- Critical Dates for the Issue of Plans & Specifications
- Early Bid Packages & Procurement of Long Lead-Time Items
- Shop Drawings, Submittals, Fabrication & Delivery of Long Lead Items
- Schematic & Design Development Estimates
- Sub/Vendor Bidding Process
- Guaranteed Maximum Price
- Permitting
- Start of Construction
- Construction Durations
- Substantial Completion Date
- Punch List
- Furniture/Fixtures/Equipment Installation by the Owner (FF & E)
- Final Completion Date
- Certificate of Occupancy Date
- Owner Occupancy Date
- During the Design Phase:
- Determine Lead Times and Task Durations as Building Systems, Materials and Equipment are selected
- Update Schedule as new information becomes available.
- During Construction:
- Update Overall Project Schedule Weekly
- Produce Three-Week Short Interval Production Schedules (SIPS)
- Review Schedule for Critical Delivery and Production Issues
- Distribute and Discuss Schedule in Weekly Jobsite Meetings with CDI Foremen and Subcontractors' Foremen.
- Our method of scheduling provides a detailed and effective tool for coordination of construction activities with the Owner.
Please feel free to check our references, and you will find CDI has a reputation and history of completing our projects on time or ahead of schedule.